1/8

Environmental Impact Assessment of Wind Energy Parks on the islands of Andros(140,3 MW), Naxos (69 MW) , Paros(64,4 MW)  and Tinos (48,6 MW)

Name of Client: ELIKA S.A.
Start date (month/year): 06/2010
Completion date (month/year): 06/2011
Duration of assignment (months): 12


Detailed Project Description:
• Data collection of the existing conditions in relation to man-made and natural environment, flora and fauna, protected areas and vulnerable spots from an ecological perspective
• Undertaking of four baseline ornithology studies in the project’s area and two baseline Ecology studies on the islands of Andros and Naxos, so that natural environment preservation is optimally secured
• Investigation of environmental impacts on the project area and the wider region, both during the project’s construction, as well as during the operation of wind parks
• A choice of the project’s site is proposed, aiming at the satisfaction of environmental criteria and at the minimization of potential environmental impacts
• Evaluation of corrective measures for the abatement of potential environmental impacts and presentation of the suggested Environmental Terms
Important environmental issues:
• Creation of a database and protection of vulnerable areas and especially those belonging to the  Natura 2000 network
• Habitat and flora protection during construction phase
• Fauna protection during wind energy parks’ operation
• Protection of man-made environment

Description of actual services provided by Enveco within the assignment:
Our staff covered the issues related to all phases of the preparation of the project. In particular, the following tasks have been covered:
Task 1: Baseline Study of the wider region of Paros, Naxos, Tinos and Andros
Task 2: Data analysis and composition of baseline ornithological and ecological assessments.
Task 3: Analysis of wind energy parks’ site choice and final decision, based on the target of minimizing negative environmental impacts on both the natural, as well as man-made environment.
Task 4: Evaluation of corrective measures for the abatement of potential environmental impacts and presentation of the suggested Environmental Terms
Task 5: Composition of a complete ESIA

Environmental Impact Assessment of Wind Energy Parks on the islands of Andros(140,3 MW), Naxos (69 MW) , Paros(64,4 MW)  and Tinos (48,6 MW)