Environmental Impact Assessment due to the construction of the crude oil transmission pipe of Thessaloniki – Skopje
Environmental Impact Assessment due to the construction of the crude oil transmission pipe of Thessaloniki – Skopje
Region: North and north-west of Thessaloniki urban agglomeration
Duration: August 1999 - 2000
Client:EL.P.ET. VALKANIKI S.A.
JOINT VENTURE FOR THE CONSTRUCTION OF THESSALONIKI – SKOPJE OIL PIPE
Main characteristics:
- Evaluation of the environmental nuisances arising during the construction phase
- Evaluation of the differentiations brought upon the environmental media during the operation phase
- Examination of the possibility to remove the pipe from the “Latomio” settlement
- Submission of study on the “Hazards and Operability of the Project”
Important environmental issues:
- Presence of structural zone and erosion zone
- Non removal of pipe from the borders of the settlement
- Differentiation in the mechanical characteristics of the soil in the work zone during the construction phase due to the compression inflicted by the vehicle and constructive machines traffic
- Differentiation of the existing land uses in the pipe occupation area
Similar projects:
- Preliminary environmental impact assessment of the Burgas – Alexandroupoli oil pipeline
- Study for the construction of rainwater pipes, Municipality of Aghios Stefanos
- Preliminary & final study for the dam of Platy, Prefecture of Rethymnon and final study for a water transmission pipeline in Messara
- Environmental impact assessment of a water supply transmission pipeline from the Aposelemi dam to Aghios Nikolaos, Lasithi