Environmental Impact Assessment due to the construction of the crude oil transmission pipe of Thessaloniki – Skopje​

Environmental Impact Assessment due to the construction of the crude oil transmission pipe of Thessaloniki – Skopje

Region: North and north-west of Thessaloniki urban agglomeration
Duration: August 1999 - 2000

Client:EL.P.ET. VALKANIKI S.A.
JOINT VENTURE FOR THE CONSTRUCTION OF THESSALONIKI – SKOPJE OIL PIPE

Main characteristics:

  • Evaluation of the environmental nuisances arising during the construction phase
  • Evaluation of the differentiations brought upon the environmental media during the operation phase
  • Examination of the possibility to remove the pipe from the “Latomio” settlement
  • Submission of study on the “Hazards and Operability of the Project”

Important environmental issues: 

  • Presence of structural zone and erosion zone              
  • Non removal of pipe from the borders of the settlement
  • Differentiation in the mechanical characteristics of the soil in the work zone during the construction phase due to the compression inflicted by the vehicle and constructive machines traffic
  • Differentiation of the existing land uses in the pipe occupation area 

Similar projects: 

  • Preliminary environmental impact assessment of the Burgas – Alexandroupoli oil pipeline
  • Study for the construction of rainwater pipes, Municipality of Aghios Stefanos
  • Preliminary & final study for the dam of Platy, Prefecture of Rethymnon and final study for a water transmission pipeline in Messara
  • Environmental impact assessment of a water supply transmission pipeline from the Aposelemi dam to Aghios Nikolaos, Lasithi